Back to Resources

Level of Development (LOD) Specification

Understanding model element development requirements at each project stage for BIM coordination and delivery

What is Level of Development?

Level of Development (LOD) defines the degree to which the geometry and associated information of a BIM element has been developed. It establishes a common language between project stakeholders about what level of detail and reliability can be expected from model elements at different project phases. LOD is not just about geometry - it includes the associated data, specifications, and documentation.

LOD vs LOD - Terminology Note

Level of Development (LOD) refers to the overall maturity of a model element. Level of Detail (also LOD) refers only to graphic appearance. Level of Information (LOI) refers to non-graphic data. Some frameworks use LOD to encompass both detail and information, while others separate them. This guide follows the BIMForum LOD Specification approach.

LOD 100 - Conceptual

Overall building massing, indicative area, height, volume, location, and orientation

Definition

  • Elements are represented graphically with a symbol or generic representation
  • Information derived from other elements (not the element itself)
  • Approximate quantities, size, shape, location, and orientation may be derived
  • Non-geometric data or line work, such as cost-per-square-metre estimates

Typical Project Stage

  • AU: Schematic Design / Concept Design
  • UK: RIBA Stage 1-2 (Preparation & Briefing, Concept Design)
  • US: Pre-Design / Programming

Example Elements

Walls

Shown as single lines or simple planes. No material layers defined. Approximate locations based on space planning.

Doors & Windows

May be indicated by symbols only, or as simple voids. No specific sizes, types, or schedules.

Structure

Building footprint and approximate height. Structural system type may be noted but not modeled.

MEP Systems

Major plant spaces identified. No equipment or distribution modeled. Allowances for risers and plantrooms.

Authorised Uses

  • Conceptual visualisation and massing studies
  • Preliminary area and volume calculations
  • Early-stage cost estimates (order of magnitude)
  • Site analysis and orientation studies
  • Not suitable for coordination or quantity takeoff

LOD 200 - Schematic

Elements modeled as generic systems or assemblies with approximate quantities, size, shape, location

Definition

  • Elements are graphically represented as a generic system, object, or assembly
  • Approximate quantities, size, shape, location, and orientation are modeled
  • Non-graphic information may be attached to the element
  • Geometry is approximate but recognisable as the intended element type

Typical Project Stage

  • AU: Design Development
  • UK: RIBA Stage 2-3 (Concept Design, Spatial Coordination)
  • US: Schematic Design

Example Elements

Walls

Generic wall types with approximate thickness. Exterior vs interior differentiated. No specific material layers or components.

Doors & Windows

Generic types placed with approximate sizes (e.g., "single door 900mm"). No hardware, frame details, or specific product selections.

Structure

Structural grid established. Column and beam locations approximate. Slab zones indicated. Member sizes not finalised.

MEP Systems

Major equipment sized and located approximately. Main distribution routes indicated. Placeholder spaces for coordination.

Authorised Uses

  • Analysis of design options
  • Spatial coordination between disciplines
  • Preliminary cost estimates
  • Early clash detection (major clashes)
  • Building performance analysis (preliminary)
  • Not suitable for detailed quantity takeoff or fabrication

LOD 300 - Detailed Design

Elements modeled as specific systems with accurate quantity, size, shape, location, and orientation

Definition

  • Elements are graphically represented as a specific system, object, or assembly
  • Accurate quantity, size, shape, location, and orientation are modeled
  • Element can be measured directly from the model without reference to non-modeled information
  • Information can be used for construction documentation

Typical Project Stage

  • AU: Detailed Design / Documentation
  • UK: RIBA Stage 3-4 (Spatial Coordination, Technical Design)
  • US: Design Development / Construction Documents

Example Elements

Walls

Specific wall types with defined layers and materials. Accurate dimensions. Fire ratings assigned. Quantities extractable for takeoff.

Doors & Windows

Specific types, sizes, and configurations selected. Schedule data complete. Frame types defined. Hardware groups assigned.

Structure

Designed member sizes and materials. Connection types indicated. Reinforcement schedules for concrete. Steel connections shown conceptually.

MEP Systems

Equipment make and model identified. Duct and pipe sizes determined. Routing complete. Loads and capacities assigned.

Authorised Uses

  • Construction documentation
  • Accurate quantity takeoff for estimating
  • Detailed clash detection and coordination
  • Permit submissions
  • Procurement specifications
  • Not suitable for direct fabrication (additional detailing required)

LOD 350 - Construction Documentation

Elements modeled with detail for coordination between disciplines and trades

Definition

  • All LOD 300 requirements plus coordination information
  • Parts necessary for coordination with adjacent elements are modeled
  • Supports and connections to other building systems shown
  • Interface elements between disciplines included

Typical Project Stage

  • AU: Construction Documentation / Tender
  • UK: RIBA Stage 4 (Technical Design)
  • US: Construction Documents

Example Elements

Walls

All LOD 300 plus: cavity closers, lintels at openings, movement joints, penetration sleeves, fire stopping locations.

Doors & Windows

All LOD 300 plus: frame profiles, threshold details, weather seals, structural supports for openings.

Structure

All LOD 300 plus: cast-in items, embed plates, penetrations, interface with cladding supports, edge conditions.

MEP Systems

All LOD 300 plus: hangers and supports, access panels, coordination sleeves, insulation, clearance zones.

Authorised Uses

  • Trade coordination and 4D planning
  • Detailed clash detection across all disciplines
  • Generation of construction drawings
  • Tender documentation
  • Work packaging and sequencing
  • Basis for shop drawing development

LOD 400 - Fabrication

Elements modeled with sufficient detail and accuracy for fabrication and assembly

Definition

  • Elements are modeled at sufficient detail for fabrication
  • Detailing, fabrication, assembly, and installation information included
  • Specific manufacturer product models with exact geometry
  • Model can drive CNC machines or robotic fabrication directly

Typical Project Stage

  • AU: Construction / Shop Drawings
  • UK: RIBA Stage 5 (Manufacturing & Construction)
  • US: Construction Administration

Example Elements

Structural Steel

Exact member profiles, connection plates, bolt holes, welds, camber, coatings. Model ready for CNC fabrication.

Precast Concrete

Panel geometry, edge profiles, reveals, embedded items, lifting inserts, reinforcement, mix specifications.

MEP Equipment

Manufacturer-specific models with exact dimensions, connection points, service clearances, weight, electrical requirements.

Curtain Wall

Exact mullion profiles, glass types by panel, bracket locations, thermal breaks, gaskets, panel fabrication details.

Authorised Uses

  • Direct-to-fabrication (CNC, 3D printing)
  • Shop drawing generation
  • Assembly instructions
  • Material ordering and cutting lists
  • Quality control and verification
  • Typically developed by fabricators/subcontractors

LOD 500 - As-Built / Operations

Elements verified as constructed and ready for facilities management

Definition

  • Elements are field-verified representations of as-built conditions
  • Accurate to the constructed state (not just design intent)
  • Includes operations and maintenance data
  • Suitable for handover to facility management

Typical Project Stage

  • AU: Practical Completion / Handover
  • UK: RIBA Stage 6 (Handover)
  • US: Construction Closeout

Key Data Requirements

Spatial Verification

Field-verified locations matched to as-built survey. Deviations from design documented. Point cloud comparisons.

Product Data

Installed product details: manufacturer, model, serial numbers, warranty information, installation dates.

O&M Information

Maintenance schedules, spare parts lists, supplier contacts, operating manuals linked or embedded.

Commissioning Data

Test results, commissioning certificates, performance verification, balancing reports for MEP systems.

Authorised Uses

  • Facility management and operations
  • Maintenance planning and scheduling
  • Space management
  • Asset management systems (CMMS/CAFM)
  • Future renovation and refurbishment planning
  • Digital twin foundation

LOD Comparison by Element Type

Element LOD 100 LOD 200 LOD 300 LOD 350 LOD 400
Wall Single line Generic thickness Specific type & layers + openings, supports Shop-ready panels
Door Symbol only Generic size Type, hardware group + frame, threshold Manufacturer model
Column Grid intersection Generic shape Sized member + connections, embeds Fabrication model
Duct Zone allocation Approximate route Sized and routed + supports, access Fabrication spools
Light Fixture Lighting zones Generic symbol Specified type + mounting, power Exact product model